Precautions for hoisting seamless pipes

Keywords: seamless pipe hoisting, seamless steel pipe
Seamless pipe/tubing hoisting is an important engineering operation, and the following points need to be noted:

1. Reasonable selection of lifting equipment: According to the weight and length of the seamless steel pipe, select appropriate lifting equipment, such as cranes, cranes, etc. Make sure the rated lifting capacity of the lifting equipment matches the weight of the seamless steel pipe.

2. Check the lifting tools: Before lifting, check the lifting tools to ensure that they are intact, such as slings, hooks, lifting straps, etc. Avoid using damaged or aging lifting tools to ensure lifting safety.

3. Determine the lifting points and lifting methods: According to the center of gravity and structural characteristics of the seamless steel pipe, reasonably determine the lifting points and lifting methods. The lifting point should be selected at a stable position of the seamless steel pipe, and the support and protection of the seamless steel pipe during the lifting process should be taken into consideration.


 seamless pipe


4. Make a good hoisting plan: Before hoisting, make a detailed hoisting plan, taking into account the environmental factors, engineering requirements, and personnel safety of the construction site. Ensure that all operations are carried out in an orderly manner during the hoisting process.

5. Safe operation: During the hoisting process, safe operating procedures must be followed, and dangerous behaviors such as overloading, sudden movements, or emergency stops are strictly prohibited. Operators should be familiar with operating procedures and be equipped with necessary safety protection measures, such as helmets and seat belts.

6. Check the status of seamless steel pipes: Before hoisting, the seamless steel pipes must be inspected to ensure that they are free from damage, cracks, deformation and other quality problems. If quality problems are found, the seamless steel pipe should be processed or replaced in time to avoid safety hazards during the hoisting process.

7. Reasonable arrangement of personnel: Hoisting operations require reasonable arrangement of personnel, including crane operators, signalmen, hoisting commanders, etc. Operators should have relevant certificates and experience, and maintain good communication and coordination to ensure the safety and efficiency of hoisting operations.

8. Monitor the hoisting process: During the hoisting process, a dedicated person should monitor to ensure that the hoisting operation complies with the plan and specification requirements. At the same time, abnormal situations during the hoisting process should be discovered and dealt with in a timely manner to ensure the smooth progress of the hoisting operation.

In short, the hoisting of seamless steel pipes needs to follow strict operating procedures and safety requirements, and make full preparations before hoisting to ensure safe and efficient hoisting.


Go here to learn more about "Recommendations for long-term storage and maintenance of seamless tubes"